| Method Statement |
|
Date Created
|
| |
26-03-2026
|
|
Site Reference/Job Number
|
| |
GNR260052
|
|
Created By
|
| |
Tom
|
|
Client Name
|
| |
Anne Rozenbrovek
|
|
Client Email
|
| |
westellahall@gmail.com
|
|
Send RAM's To Client Email
|
| |
|
|
Site Address
|
| |
West Ella Hall, West Ella Hull HU10 7SD Map It
|
|
Site Image
|
| |
IMG_63692.JPG
|
|
Internal Reference:
|
| |
West Ella Lodge
|
|
Start Date
|
| |
07/03/2026
|
|
End Date
|
| |
10/04/2026
|
|
Housekeeping
|
| |
- Allocate 10-15 minutes each day to clean down and tidy work areas and scaffold.
- With 1 hour Friday afternoons for full site clean down including scaffold areas and ground level.
- All debris to be either cleared to site skip or cleared from site to skips at company yard.
- Site and work areas responsibility to all operatives on site to ensure kept clean and tidy.
- If scaffold is over public areas, ensure scaffold netting in place and scaffold boards are covered.
- Ensure all cigarette butts are disposed in safe and hygienic manner.
|
|
Imagery
|
| |
|
|
Send Copy To Yourself
|
| |
|
| Nearest Hospital |
|
Nearest Hospital
|
| |
Hull Royal Infirmary
|
|
Site Setup
|
| |
- Welfare Facilities
- Off site waste disposal
- Emergency Procedure
- First Aid
- Storage Compound
|
|
Welfare Facilities
|
| |
Welfare arrangements are supplied by the client or principal contractor.
These should be in line with Schedule 2 of the Construction Design & Management Regulations 2015 (CDM).
All sites are to have a minimum amount of welfare facilities available for workers, which include the following:
• Toilets
• Washing facilities
• Drinking water
• Changing rooms and lockers
• Heating
• Rest facilities
|
|
Emergency Procedures
|
| |
The client or principal contractor will ensure that the existing site emergency procedures are followed and that relevant information is given to operatives at time of induction or when changes are made to procedures.
The principal contractor is responsible for ensuring that all operatives under their control adhere to the site emergency procedures at all times.
The closest hospital is:
Hull Royal Infirmary
Anlaby Road, Hull, HU3 2JZ
|
|
First Aid
|
| |
Refer to on site safety notice boar / site file for all first aid information.
A first aid box with enough equipment to facilitate the number of operatives on site will be provided by the Principal Contractor.
Principal contractor will nominate and appointed person to take care of first aid arrangments.
Number of appointed first aiders shall be dependedt upon the number of employees on site.
|
|
Off Site Waste Disposal
|
| |
Due to the nature of the property, limited parking, and access constraints we will place a skip at our premises for the disposal of waste as works progress.
Skips will be provided off-site for the duration of the work.
The collection of waste will be carried out on a regular basis using an appropriate vehicle.
Waste will be carried to our premises to be disposed of.
Waste streams will be separated for recycling where appropriate.
|
|
Storage Compound
|
| |
All COSHH relevant materials will be stored on site in accordacne with relavant regulations.
A secure site compound will be provided for the duration of the work.
|
|
PPE Requirements
|
| |
- Hi-Vis Vests
- Safety Boots
- Hard Hats
- Face Fit Masks (FFP3)
- Protective gloves (BS EN 388:2016+A1:2018)
- Hearing Protection Ear Muffs to (BS EN 352-1)
- Safety Goggles
|
|
Training & Legislation
|
| |
All operatives are adequately trained to carry out required tasks.
All site operatives hold current certification and have the following training.
- CSCS Certification
- Working at heights training
Legislation
- Health and Safety Work Act 1974
- The Management of Health and Safety at Work Regulations 2006
- The Control of Asbestos Regulations 2012
- Provision and Use of Work Equipment Regulations (PUWER) 1998
- Control of Substances Hazardous to Health Regulations 2002
- The Work at Height Regulations 2005
- The Personal Protective Equipment at Work Regulations 2002
- The Manual Handling Operations Regulations 1992
- The Construction (Design and Management) Regulations 2015
|
|
Description of activity
|
| |
As outlined by our previous specification document. GNR-260052
|
| Additional work areas |
|
Operatives Assigned To Project
|
| |
- Charlie Bedford
- Jonathan Clark
- Thomas Mackley
- Carl Tumman
- Scaffolding Contractor
|
| Tools & Equipment |
|
Tools/Equipment
|
| |
|
|
Battery Operated
|
| |
- Drill
- Impact Driver
- Grinder
- Circular Saw
- Multi Tool
- SDS Drill
- Add More
|
|
Equipment
|
| |
|
| Materials |
|
Materials
|
| |
- Timber/Wood
- Rolled Lead sheet
|
|
Timber/Wood
|
| |
- 25mm x 50mm Battens
- Exterior Grade Ply
|
| Project Health & Safety Monitoring |
|
Supervision of the work will be carried out by;
|
| |
|
|
Overall Health & Safety monitoring will be conducted by;
|
| |
- Oliver Neal
- Thomas Mackley
|
|
Add Signature Sheet
|
| |
- Yes, Include Signature Sheet
|
| Known Hazards |
|
GNR Risk Assessments
|
| |
- GNR002 Delivery of Materials
- GNR003 Manual Handling
- GNR004 Working at Height
- GNR005 Use of Ladders
- GNR008 Disc Cutters & Abrasive Wheels
- GNR009 Lead Work
- GNR010 Lead Welding
- GNR012 Storage & Disposal of Waste Materials
- GNR020 Dust
- GNR041 Lead Sealant
- GNR047 Vibration
- GNR048 Noise
|
| COSHH Register |
|
COSHH Assessments
|
| |
- CA/019 Lead
- CA/020 Patination Oil
|
|
Warnings
|
| |
- Flammable
- Gas under pressure
|